Library of Birmingham – Report 1

The site has been through investigations, archaeology and preparation. Now Carillion Piling are working on site for the installation of foundation and basement wall piles. This was the scene on 25 Jan 10 afternoon. This will continue through to April this year.

Geoff Caine

(Click on image for larger view then click on the new view for more detail)

If you have any remarks to make about incidents, etc, on Health & Safety hazards, environmental nuisance or personal issues or, informative events you would like held,  phone 0800 1385651 or email sdingle@carillionplc.com .