Centenary Square Redevelopment Update

The Westside BID (Business Improvement District) passes on this report on progress and finish dates.

 

·   Trees being planted around Hall of Memory and two planters

·    Baskerville font returned to site.

·      Lighting columns being installed in April

·      Ground workers completing the paving and expected off site by end of May

·       Bolton Watt and Murdock, plus Birmingham Family returning to site in June

·       During June site set up being dismantled and square cleaned plus snagging

·        July 3rd Centenary Square will be opened in full, and water feature turned on.

The Granite finishes to front of ICC will be left off along with 5  lighting columns to the front of ICC/Symphony Hall/Hyatt. These will be installed after Symphony Hall extension is completed.

Symphony Hall Extension starting on site in July  2019

Add a comment...

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s