The Westside BID (Business Improvement District) passes on this report on progress and finish dates.
· Trees being planted around Hall of Memory and two planters
· Baskerville font returned to site.
· Lighting columns being installed in April
· Ground workers completing the paving and expected off site by end of May
· Bolton Watt and Murdock, plus Birmingham Family returning to site in June
· During June site set up being dismantled and square cleaned plus snagging
· July 3rd Centenary Square will be opened in full, and water feature turned on.
The Granite finishes to front of ICC will be left off along with 5 lighting columns to the front of ICC/Symphony Hall/Hyatt. These will be installed after Symphony Hall extension is completed.
Symphony Hall Extension starting on site in July 2019